This page was exported from Free Exams Dumps Materials [ http://exams.dumpsmaterials.com ]
Export date: Sat Nov 23 9:51:02 2024 / +0000 GMT

[May 24, 2023] BICSI RCDDv14.1 Real Exam Questions and Answers FREE [Q168-Q182]




[May 24, 2023] BICSI RCDDv14.1 Real Exam Questions and Answers FREE

Pass BICSI RCDDv14.1 Exam Info and Free Practice Test

QUESTION 168
A program management team is invited to a company’s annual strategy planning session The CEO discusses the mission and vision of the organization, and how the strategic plan will create opportunities to fulfill them How can the program manager use the company’s vision to establish a program?

 
 
 
 

QUESTION 169
The program selection committee presents several programs for approval:

Which program was selected based solely on a three-year return on investment?

 
 
 
 

QUESTION 170
A biometrics firm has a facial recognition program with multiple components and project managers The project manager from the mobile device division escalates a vendor-related risk to the program manager After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of Impact and probability of occurring What should the program manager do first?

 
 
 
 

QUESTION 171
An initiative involves the development of new technology and leverages existing technologies It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place. In what phase is the nsk management plan created?

 
 
 
 

QUESTION 172
A global communications company’s cloud-based platform will host its video network using both on – and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.
What should the program manager do to resolve competing resource needs within components that could impact the entire program’s overall delivery date?

 
 
 
 

QUESTION 173
What is the MINIMUM clearance needed between the front of the telephone booth and any wall or fixture for most installations?

 
 
 
 
 

QUESTION 174
An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design. Which of the following information about the site shall be included?

 
 
 
 

QUESTION 175
A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.
What should the program manager do next?

 
 
 
 

QUESTION 176
The program manager completed the program’s benefits analysis and planning activities. What will this ensure tor the program?

 
 
 
 

QUESTION 177
Which of the following is the CORRECT calculation to determine equipment heat load resulting from its power (W) consumption?

 
 
 
 

QUESTION 178
A project’s installation start involves a Kickoff Meeting and the General Contractor’s Coordination Meeting. As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

 
 
 
 
 

QUESTION 179
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?

 
 
 
 
 

QUESTION 180
A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters To ensure the realization of long-term benefits what should the program manager use?

 
 
 
 

QUESTION 181
A commercial office building floor has a usable floor space of ≈1858 m2 (20,000 ft2). What is the MINIMUM number of 103 mm (4 trade size) conduits that shall be required to interconnect the telecommunications rooms on this floor?

 
 
 
 

QUESTION 182
Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?

 
 
 
 

Latest RCDDv14.1 Exam Dumps BICSI Exam: https://www.dumpsmaterials.com/RCDDv14.1-real-torrent.html

Post date: 2023-05-24 16:29:09
Post date GMT: 2023-05-24 16:29:09
Post modified date: 2023-05-24 16:29:09
Post modified date GMT: 2023-05-24 16:29:09