This page was exported from Free Exams Dumps Materials [ http://exams.dumpsmaterials.com ] Export date:Thu Nov 21 13:43:12 2024 / +0000 GMT ___________________________________________________ Title: [May 24, 2023] BICSI RCDDv14.1 Real Exam Questions and Answers FREE [Q168-Q182] --------------------------------------------------- [May 24, 2023] BICSI RCDDv14.1 Real Exam Questions and Answers FREE Pass BICSI RCDDv14.1 Exam Info and Free Practice Test QUESTION 168A program management team is invited to a company’s annual strategy planning session The CEO discusses the mission and vision of the organization, and how the strategic plan will create opportunities to fulfill them How can the program manager use the company’s vision to establish a program?  Define the program and component projects to enable the fulfillment ol strategic goals  Set the priority matrix and map the projects” priorities that will be included in the program  Define the program roadmap, and highlight the individual protects’ benefits  identity program benefits that will enable the fulfillment of strategic goals QUESTION 169The program selection committee presents several programs for approval:Which program was selected based solely on a three-year return on investment?  Program A  Program B  Program C  Program D QUESTION 170A biometrics firm has a facial recognition program with multiple components and project managers The project manager from the mobile device division escalates a vendor-related risk to the program manager After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of Impact and probability of occurring What should the program manager do first?  Obtain a risk reserve from the executive sponsor and execute a contingency plan  Communicate the risk to all project managers to manage at the component level  Add the risk details and analysis to the program risk register  Brainstorm with the project manager to develop an appropriate risk response. QUESTION 171An initiative involves the development of new technology and leverages existing technologies It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place. In what phase is the nsk management plan created?  Program definition  Program execution management  Program delivery  Program risk management planning QUESTION 172A global communications company’s cloud-based platform will host its video network using both on – and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.What should the program manager do to resolve competing resource needs within components that could impact the entire program’s overall delivery date?  Require project managers to perform resource levelling in their schedules to automatically take into account availability and dependencies tor key resources.  Revisit assignments on a weekly basis to manually level resources thereby limiting burn-out and preventing underutilization  Optimize integration of the component projects by working with the project managers to align resource skill sets and availability to the program  Improve communications between the project managers to gain efficiencies in resource assignments QUESTION 173What is the MINIMUM clearance needed between the front of the telephone booth and any wall or fixture for most installations?  300 mm (12 in)  450 mm (18 in)  610 mm (24 in)  914 mm (36 in)  2.4 m (8 ft) QUESTION 174An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design. Which of the following information about the site shall be included?  Sustainability requirements  Suitability requirements  Access and/or service provider requirements  Designer requirements QUESTION 175A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.What should the program manager do next?  Escalate the issue to the stakeholder’s supervisor.  Escalate the issue to the program governance board as delays will impact the program  Update the program risk register to reflect a realized risk and execute the documented risk response  Attempt to call the key stakeholder, if unsuccessful, visit their office to identify potential risks QUESTION 176The program manager completed the program’s benefits analysis and planning activities. What will this ensure tor the program?  Information necessary to establish key benefit performance indicators  A transition plan to facilitate the ongoing realization of benefits  A plan to monitor performance due to operational, financial, and benefits changes  A benefits management plan to guide the work through the remainder of the program QUESTION 177Which of the following is the CORRECT calculation to determine equipment heat load resulting from its power (W) consumption?  W x 1.414  W x 1.732  W x 2.235  W x 3.412 QUESTION 178A project’s installation start involves a Kickoff Meeting and the General Contractor’s Coordination Meeting. As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)  Project submittal approval process  RFI process  Payment procedures  Punch List process  Project start and completion dates QUESTION 179Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?  Verify the equipment controls are in the proper operating position.  Train workers to perform the LOTO process.  Apply appropriate tags both locally and remotely.  Confirm the device is de-energized by proving it will not run when started.  Confirm all unnecessary items have been removed from the area. QUESTION 180A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters To ensure the realization of long-term benefits what should the program manager use?  Benefits register  Benefits sustainment plan  Benefits management plan  Benefits transition plan QUESTION 181A commercial office building floor has a usable floor space of ≈1858 m2 (20,000 ft2). What is the MINIMUM number of 103 mm (4 trade size) conduits that shall be required to interconnect the telecommunications rooms on this floor?  0  1  2  3 QUESTION 182Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?  General Contractor  ICT distribution designer  Client  Architect. Engineering, Consultant Team  Loading … Latest RCDDv14.1 Exam Dumps BICSI Exam: https://www.dumpsmaterials.com/RCDDv14.1-real-torrent.html --------------------------------------------------- Images: https://exams.dumpsmaterials.com/wp-content/plugins/watu/loading.gif https://exams.dumpsmaterials.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2023-05-24 16:29:09 Post date GMT: 2023-05-24 16:29:09 Post modified date: 2023-05-24 16:29:09 Post modified date GMT: 2023-05-24 16:29:09